Studies completed
16 / 19
3 active workstreams remain open
Executive compliance dashboard
A real-time leadership view of study progress, FERC filing readiness, and regulatory milestones for the Nuyakuk River Hydroelectric Project.
Studies completed
16 / 19
3 active workstreams remain open
Days until License Application
350
Calculated from Jan. 15, 2025 USR meeting baseline
Last FERC filing
USR (Dec 2024)
Latest study update recorded Jan 12, 2025
Project context
The Nuyakuk River Hydroelectric Project is a proposed 10–12 MW run-of-river hydroelectric project on the Nuyakuk River serving Dillingham, Aleknagik, Koliganek, New Stuyahok, Ekwok, and Levelock. The tracker gives Nushagak leadership a concise view of study completion, open regulatory workstreams, and filing readiness as the cooperative moves through the FERC Integrated Licensing Process.